Tired of ads? Enjoy an ad-free experience by signing up.
👩‍🍳 How we use AI at Tech in Asia, thoughtfully and responsibly.
🧔‍♂️ A friendly human may check it before it goes live. More news here

Microsoft launches data center plan to cut power costs, water use

Microsoft has launched a new initiative to reduce water use and manage electricity costs at its US data centers.

The company said it will work with local utilities to expand power supply and infrastructure when needed, and pay utility rates that fully cover its electricity costs.

Microsoft also plans to replenish more water than its data centers consume, and will publish water-use data for each US data center region.

The move follows comments from US President Donald Trump, who said Microsoft would make changes to its AI infrastructure plans to prevent rising electricity prices for consumers due to data center demand.

🔗 Source: Reuters

🧠 Food for thought

Implications, context, and why it matters.

Microsoft’s commitments may not prevent residential rate increases if utility regulators fail to enforce cost separation

  • The Public Utilities Commission of Ohio (PUCO), the state regulator of electric utilities, ordered AEP Ohio (a large Ohio electric utility) to adopt data center specific tariffs (specialized electricity rate structures) 1. Its case logged 30,000 megawatts (MW) of load requests from data centers (requests for large power connections) 2. Studies find even a fraction would overload the grid in central Ohio, so regulators need binding rules with minimum demand charges (fixed fees based on reserved capacity) and exit fees (charges that cover utility investments if a large customer departs early) to avoid stranded costs.
  • Microsoft says it has backed nearly 8 gigawatts (GW) of new generation in the Midwest, which exceeds its current regional use 3. Utilities still must decide whether to assign grid upgrade costs to data centers through tariffs or spread them across all ratepayers.

Independent power producers can benefit from utilities’ need for new generation capacity and grid infrastructure

  • Analysts expect AI data centers to use half of new US power by 2030 4. Utilities in data center heavy regions will issue requests for proposals (RFPs) for capacity. That creates near term work for independent power producers (IPPs), non utility generation companies that offer nuclear, natural gas or renewables.
  • More data centers secure behind the meter power (on site generation and storage dedicated to a facility) because grid connection waits exceed four years in primary markets 5. That boosts demand for colocated battery storage plus private wire transmission (direct lines from plants to data centers), which in Europe, the Middle East and Africa (EMEA) can cut power costs by 40% versus grid power 5. The Electric Reliability Council of Texas (ERCOT), the state’s grid operator, expects the state must more than double capacity by 2031 due to data center growth 6. Utilities will build new substations and transmission lines, plus demand response systems (tools that shift or curb usage during peak periods).

Recent Microsoft developments

Stay ahead in Asia’s tech landscape

You've reached your 2 free content limit for the month. Sign up for free to read the full story.

🏄 For casual readers / 👶 Free

Basic

US$0

Free forever

Get instant access to this article and more every month

0 premium content

Unlimited news briefs

5

5 articles

Ad-free reading experience

Just US$0 per day

⌛Sign up in 20s. No payment details needed.

📖 For learners / 👍 Starter

Lite

US$4.92/month

Billed annually at US$59/year

Get instant access to this article and more every month

4

4 premium content

Unlimited news briefs & articles

Ad-free reading experience

Just US$0.17 per day

Cancel anytime

Our subscriber community includes professionals from these companies:

Stay updated on the go with our mobile app.

Get latest insights with smoother, more personalized experience through TIA mobile app.