Digital Edge to build $4.5b Indonesia data center campus
Digital Edge, an Asian digital infrastructure company backed by Stonepeak Partners, plans to invest US$4.5 billion to develop a large data center campus in Indonesia.
The CGK Campus, located in Bekasi near Jakarta, will be an AI-ready hyperscale facility with an initial capacity of 500 MW, potentially expanding to 1 GW.
Construction will occur in phases, with the first building expected to be operational by Q4 2024 and two additional buildings by mid-2025.
The campus will be supported by Indonet, Digital Edge’s Indonesian telecom subsidiary.
The company aims to address Indonesia’s fast-growing digital economy, which has outpaced infrastructure development.
🔗 Source: Digital Edge
🧠 Food for thought
Implications, context, and why it matters.
Key operational prerequisites for the 500 MW campus are not addressed in the announcement
- The ability to deliver 500 megawatts of IT capacity, with a path to 1 gigawatt, should be validated.
- Grid interconnection capacity for the Bekasi site should be confirmed with the state utility PT PLN (Persero).
- In 2022, installed system capacity and peak load figures for DKI Jakarta (Jakarta’s special capital region) were cited by PLN 1. A campus of this size would require substantial allocation.
- Another operator’s 500 MW plan has been backed by a 30 MVA (megavolt-ampere) power purchase agreement. The gap suggests how hard large blocks of power can be secured 2.
- Environmental permits should be confirmed. A sustainable energy path should be set to meet Digital Edge’s stated goal of achieving carbon neutrality by 2030 1.
Bekasi campus could shift interconnection patterns east of Jakarta, but cloud on-ramp specifics need verification
- Content Delivery Networks (CDNs), services that cache and deliver content closer to end users, and cloud interconnect brokers may find room to expand at a 500 MW carrier-neutral campus.
- The Bekasi location sits on Jakarta’s eastern edge, about 40 kilometers from Digital Edge’s downtown facilities. The build could pull traffic away from the city’s usual hubs.
- Third-party carriers can place a Point of Presence (PoP), a network operator’s physical connectivity site, early to reach hyperscale and AI tenants sooner.
- Service providers can inventory current Jakarta cloud on-ramps, including AWS Direct Connect at the NTT Jakarta 2 data center with 100 Gbps (gigabits per second) dedicated connections 3, to time market entry.
- Teams can also review current interconnect options for AWS 4. They can check Google Cloud via Dedicated Interconnect colocation facilities 5 plus Azure ExpressRoute 6.
Stay updated on the go with our mobile app.
Get latest insights with smoother, more personalized experience through TIA mobile app.